“ZTR” PrJSC has signed the contract for equipment delivery for constructed HPP Sashuala, Georgia

“ZTR” PrJSC has signed the contract for equipment delivery for constructed HPP Sashuala, Georgia

In October 2018, ZTR PrJSC signed the contract for equipment delivery for constructed Hydraulic Power Plant Sashuala, located in Guria area. The contract is purposed for delivery of the transformer TDTN-16000/110.

To maximize the development of the country's hydro potential in Georgia, there is the program for development of small-capacity Hydraulic Power Plants, one of the stages of such development was construction of Hydraulic Power Plant (HPP) Sashuala. To connect to the network of the new Hydraulic Power Plants, extension of S/S “Chokhatauri” is implemented by means of installation of new power transformer rated for 16 MVA/110kV.

Preparation works related to this project were started in early 2018, during which negotiations were held with both the final Customer, and the General Contracting organization appointed for construction.

In addition to “ZTR” PrJSC, the Turkish manufacturers struggled for this project, but decisive factors in choosing the Supplier were the best price bid and the fact that “ZTR” PrJSC has gained the reputation as the manufacturer of high-qiality and reliable equipment in the market of Georgia.

At the moment, the transformer is manufactured and shipped to the Customer. Installation is pre-scheduled for April-May 2019.
Upgraded substation is part of the largest distribution company in Georgia, ENERGO PRO, so successful implementation of this order will be the foundation for further fruitful cooperation with Georgian partners.

REFERENCE: “Zaporozhtransformator” PrJSC is one of the largest manufactures of transformer equipment in the world having experience of deliveries to 88 countries. The Company manufactures oil-filled power transformers, electric reactors, controlled shunt reactors.

22.02.2019